SEPTA crews will be working on sections of both the inbound and outbound platforms at Glenside Station. Crews will be demolishing the portion of platforms in place between the top of the stairwells and the end of the bridge deck over Easton Road.
Project Location and Hours
The work takes place at Glenside Station platforms over Easton Road from Monday, April 7 through Friday, April 18, 2025.
Normal construction hours are 9 am to 3 pm Mondays-Fridays.
Impact on Riders
There is no impact on riders. All service operates as normal weekdays during this scheduled work.
Impact on Area Traffic
To facilitate the platform construction, and as a safety precaution, a single-lane restriction will be in place underneath the bridge on Easton Road between Glenside Avenue and Mt. Carmel Avenue. Flaggers will be in place at both intersections: Easton Road and Mt. Carmel Avenue and Easton Road and Glenside Avenue
- At least one sidewalk will always be accessible
- Pedestrian access to businesses will be available during construction.
Project Details
This work is part of SEPTA’s rehabilitation of the bridge over Easton Road and part of the Authority’s continuing efforts to bring its bridge structures into a state of good repair.
Rehabilitation efforts include structural repairs, such as concrete repairs to the abutment walls, center pier support and bridge superstructure as well as waterproofing of bridge superstructure. In addition, crews will perform partial platform replacement and repairs at Glenside Station.